| NPS | SCH / WT | Length (m) | Root method | Fill method | Joints | Root mass | Fill mass |
|---|
Each row uses its own welding method combination. Bevel parameters (root opening, root face, bevel angle, repair allowance) are taken from the Single pipe size sub-tab.
| NPS (in) |
OD (mm) |
Wall thickness (mm) | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Reference: ASME B36.10M (carbon & low-alloy steel pipe). Wall thickness shown in millimetres. Empty cells indicate the schedule is not standard for that pipe size.
| Stamp | Name | Process | Position | OD range | Thickness range |
|---|
| Stamp | Name | Process | Position | Service |
|---|
| Stamp | Name | Processes | Position | OD range | Thickness range |
|---|
Based on 70% bolt yield, outer-ring reinforced spiral wound gasket. For RTJ joints, repeat the 100% chase pass. For other gasket types, consult manufacturer.
Bolt count auto-fills per ASME B16.5 when you change flange size or class. You can override manually if needed.
Tighten in three passes (30% → 60% → 100%) following this diametrically-opposed sequence at every stage. After the 100% pass, do a final clockwise chase pass at 100% torque until uniform. RTJ joints require a second 100% chase pass.
100% torque values in N·m. Updates automatically when you change the lubricant above.
| Welder | Joints | Dia/inch | Tested | Repair | Repair % | Last weld |
|---|
| NPS (in) |
OD (mm) |
Seam (m) |
Joints per day (avg) | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Each cell shows joints/day based on bevel cavity volume only (cap reinforcement excluded). Bevel parameters (root opening, root face, bevel angle) are taken from the Single pipe size tab. Joint volume = groove area × pipe circumference.
| NPS (in) |
OD (mm) |
Seam (m) |
Joints per day (Shop / Field) | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Each cell shows joints/day for a Shop welder (top, blue) and a Field welder (bottom). Shop welders work in pre-fab areas with better access and lighting; field welders work in-situ with scaffold, position constraints (5G/6G), and tighter access. The model accounts for both welding time and fit-up overhead — fit-up is shorter in shop (controlled alignment) than in field. Joint time = welding time + fit-up time; productive shift is 360 min/day. Bevel parameters (root opening, root face, bevel angle) are taken from the Single pipe size sub-tab.
| Process | Pass | Voltage (V) |
Current (A) |
Travel speed (mm/min) |
HI gross (kJ/mm) |
HI net (kJ/mm) |
Status |
|---|
Heat input formula: HI = (V × I × η × 60) / (TS × 1000), where η is the process arc efficiency per AWS D1.1 / EN 1011-1. HI gross uses η = 1.0 (raw arc energy); HI net applies the process-specific efficiency and is the value typically cited in WPS / PQR documents. Acceptance ranges are typical industry practice — always defer to the project specification.
Formulae
CEIIW = C + Mn/6 + (Cr+Mo+V)/5 + (Cu+Ni)/15.
Preheat is calculated per EN 1011-2 Method B, using CET, wall thickness, diffusible hydrogen
and heat input. HAZ hardness uses the Yurioka empirical correlation (CE-based).
Always cross-check against the project specification — values are advisory.